Second Public Notice of the Environmental Impact Assessment for the Upgrade and Renovation Project of the 4 × 180 m² Sintering Machines at Hebei Donghai Special Steel Group Co., Ltd.
Release date:
2022-07-22
Hebei Donghai Special Steel Group Co., Ltd. 4 × 180 m 2 Change to the Sintering Machine Upgrade and Renovation Project Environmental Impact Assessment The Two Next Information Public Notice
I. Project Overview
Eliminate the existing 2 Tai ( 2# and 4# ) 180 m 2 The old belt-type sintering machine and its auxiliary systems, in… 1# and 2# A new unit has been built at the Sintering Airport site. 360 m 2 A new-type belt sintering machine, along with a complementary mix‑preparation system, finished‑product screening system, blowers, an annular cooler, desulfurization and denitrification dust‑removal equipment, a waste‑heat recovery system, high‑ and low‑voltage switchgear rooms, and other auxiliary facilities. 1# The sintering machine shall be filed separately. 3# The sintering machine will no longer be retrofitted. 。
II. Online link to the full draft Environmental Impact Report and methods and channels for accessing the hard copy of the report
Link: https://pan.baidu.com/s/1bz4odi_uZGW2ZREoA-Nwkw Extraction code: k75w
Access to the Paper Report: The public may obtain a hard copy of the environmental impact assessment report by contacting the EIA agency or the project developer via email or mail.
III. Scope of the Public Involved in Soliciting Comments and the Duration for Submitting Feedback
Scope of the public invited to provide comments: citizens, legal entities, and other organizations within the scope of the project’s environmental impact assessment; the period for submitting comments is ten working days following the date of this public notice.
IV. Link to the Public Comments Form
Link: https://pan.baidu.com/s/1bz4odi_uZGW2ZREoA-Nwkw Extraction code: k75w
Five , Name and contact information of the relevant entity
|
1 Name and contact information of the construction entity Name: Hebei Donghai Special Steel Group Co., Ltd. Contact: Mr. Gao Phone: 15373504273 Email: 39329255@qq.com |
2 Name and contact information of the EIA preparation entity Name: Hebei Zhengrun Environmental Technology Co., Ltd. Contact: Engineer Wang Phone: 0311- 66036383 Email: 349784427 @qq.com |
Hebei Donghai Special Steel Group Co., Ltd.
July 22, 2022